07.10.25 update- Browns Trace bridge

CONSTRUCTION ACTIVITIES: This week, ECI removed the old bridge and started excavating for the new bridge. They installed stone fill on the front side of the new abutment. They are planning to drive piles for the remainder of the week. Next week they plan to start formwork and rebar for both abutments as well as start the precast retaining wall on the Northeast side of the project.

TRAFFIC IMPACT: The road will continue to remain closed. Motorists should follow detour signs.