Town of Jericho - Highway Garage Design Services RFP
Background Town of Jericho (TOJ) has retained the services of Matt Young of Ascent Consulting LLC as their Municipal Project Manager (MPM) to assist with preconstruction phase of a new Town Highway Garage. On March 5, 2024, the Town voters approved bond to spend a not to exceed amount of $4.150M for the construction of a new town maintenance facility. Soft cost will come from a separate account.
Schedule The preconstruction phase of this project is on a very tight schedule and key milestones must be met. The selected team must be ready to start work immediately.
1. Post Design Services RFP 06/14/24
2. Last day for RFI 06/24/24
3. Addendum posted 06/27/24
4. Design Services RFP Due 07/01/24 3pm EDT
5. Select Design Team 07/11/24
6. Kick-off Meeting 07/18/24
7. Phase-1 Design & Permit July 2024-Feb 2025
8. Project Bidding March 2025
9. Phase-2 Construction Start May 2025
Instructions All questions and RFP submission must be directed to Matt Young at myoung@ascentconsultingllc.com and copy Paula Carrier, Town Administrator pcarrier@jerichovt.gov